Open Questions Β· Who Must Answer What

The 13 experts and the critic raised 141 raw open questions. Deduplicated and translated into plain language, they collapse to 40, grouped by the only thing that matters for getting them closed: who has to answer. Tick a question when it is answered β€” state is saved in this browser. Items flagged W1 must be asked this week (Jul 6–10) or the mid-August go-live slips.

0/40
0 / 40 answered
Checklist state persists in localStorage on this device only β€” it is not shared between viewers.
40
questions open
3
blocking
16
this-week (W1)
6
answer owners
The 3 blocking questions β€” everything else queues behind these
  1. Do the 133 desks get live wired Ethernet, or is the office WiFi-only? Wired desks turn this from a 7-cable job into a ~150-drop structured-cabling project: different switch layer, different vendor class, and roughly double the budget. Nothing about the switch/rack PO is final until this is answered.
  2. Which building β€” name and exact address? It determines which ISPs are already live in the riser (internet in ~2 weeks vs 2 months), every landlord fit-out rule, and where the PMO questionnaire goes. Until answered, half the questions on this page cannot even be asked.
  3. Is the β‚±318,752 VAT-inc budget approved β€” plus the option calls (spare AP β‚±23,000 Β· second ISP line ~β‚±10,000–25,000/mo Β· server-room aircon Β· AV tier)? The equipment PO must go out this week: the APs and the 10G PoE++ switch are frequently 2–4-week indent (import) items in the Philippines.

1 Β· Paul / management

Decisions only management can make. Most of them gate a purchase order or an application that must leave this week.

Unblocks the ISP applications, the entire landlord questionnaire below, and the contractor accreditation clock.
The single biggest fork: live desk Ethernet β‰ˆ 150 extra drops + bigger switches β‰ˆ budget Γ—2, and it must also be pulled before the ceiling closes.
Releases the equipment PO (50% down) β€” the bare-minimum 5-AP fallback is ~β‚±230,000 but is capacity-thin for 150 staff. PH RMA runs 2–6 weeks, hence the spare.
Unblocks the two parallel ISP applications β€” provisioning is the longest pole (up to 4–8 weeks); for 150 people think 500 Mbps–1 Gbps.
Prowatcher is CCTV-first and quoted an under-spec PoE+ injector; a competing bid keeps the fair β‚±25,000–33,000 install price honest.
Decides whether the UCG-Fiber gateway + 1 AP can really be reused, or we buy new (+~β‚±45,000) / plan a cutover weekend.
Decides certificate-based WiFi login (best security) vs per-team passwords; the certificate service costs between $0 and ~$2/user/month depending on licensing.
Email collection and CCTV both trigger Philippine privacy-law paperwork (privacy notices, footage-access requests) that a named person must own.
More than ~6–8 cameras forces a dedicated NVR + more PoE ports; pulling their cables now, while the ceiling is open, is the cheapest moment there will ever be.
AV wall/ceiling drops must ride the same open-ceiling window as the WiFi cabling β€” deciding late means visible conduit later.
Log forwarding is table stakes for a cybersecurity group and cheap to configure at commissioning; retrofitting compliance later is rework.
PEZA zero-rating vs 12% VAT changes the real hardware cost; theft from unsecured fit-out sites is common in PH.

2 Β· Landlord / building PMO

A full 15-point PMO questionnaire is drafted and ready to email the day the building is named. These are the decision-critical items from it.

One phone call decides whether internet arrives in ~2 weeks or 2 months β€” the single longest lead item to mid-August.
Sets the true cost and paperwork lead of the whole fit-out; the bond alone can be months of rent.
The ceiling closes in 2–4 weeks; slow plan vetting eats the entire cable-pull window.
Discovered late, any one of these adds 1–2 weeks; the insurance certificate is needed before the installer may even mobilize.
The 4.97 sqm server room has no exterior wall and most split units allow only 15–20 m of refrigerant pipe; building AC is assumed OFF nights/weekends.
With a genset, the planned 1.6 kVA UPS rides the 10–60 s gap and the brownout problem disappears; without one, WiFi dies ~15 min into a rotational brownout.
Only the accredited FDAS firm may legally tie into the building system; the maglock cannot pass fire inspection without the release relay.

3 Β· Fit-out contractor

The construction schedule is the second critical path next to the ISP. Everything here is one site meeting.

Every cable pull (APs, AV, CCTV, desk drops if approved) must happen before it; this date anchors the whole project schedule.
Sets the cable rating we must buy (plenum vs standard), the AP mounting hardware, and the pull labor β€” needed before the cable PO.
Concrete meeting rooms need an 8th AP inside; short server-room walls leak hot air and weaken physical security.
Glass needs a maglock with fail-safe design; a solid door takes a simpler, safer electric strike.
Riding under the main permit avoids a separate engineer-signed submission β€” which costs weeks.
After the walls close this becomes rework; the phase answer decides which surge-protector model to buy.
A 4.97 sqm interior room running 300–500 W of IT load 24/7 overheats without it β€” this must be injected into the fit-out scope in July.
AP positions freeze only after the furniture/partition layout is final; the furniture spine decides how desk cabling (if approved) is run.

4 Β· Installation vendor(s)

Prowatcher and/or the competing cabling bidders, plus the UniFi distributors (MEC, iConnect).

Nobody publishes PH stock online β€” it takes a phone call; out-of-stock means a 2–4-week import that eats the schedule.
The January quote was FX-conditioned and ~29% over US list at January rates; the quoted injector cannot legitimately power the chosen APs.
A falling 1 kg AP over a desk is a liability; visible-conduit sign-off must happen before installation, not after.
This is what makes the network maintainable by whoever touches it next β€” and it costs nothing to demand up front.

5 Β· ISP(s)

Ask two providers in parallel (e.g. RISE + PLDT Enterprise or Converge) β€” do not serialize.

Existing entry β‰ˆ 2 weeks (RISE averages ~1.8); missing entry facilities commonly means 4–8 weeks β€” the difference decides mid-August.
The reused UCG-Fiber gateway takes fiber directly; a telecom-room landing adds an inter-floor riser run that the landlord may require an accredited contractor for.
Feeds the management service-level decision with real numbers instead of the β‚±10,000–60,000/mo estimate range.

6 Β· Cebu ops team on the ground

Things only someone physically in Cebu (Xerxis / office admin) can check or own.

A dead reused gateway discovered in August kills the cutover; the RF plan assumes 6 GHz (legal in PH, 5925–6425 MHz) actually works.
The moment the gear moves, the old office loses WiFi β€” this needs a named owner and a date, not an assumption.
If not, the 5G backup needs a window-mounted antenna, a longer Ethernet run, and a β‚±840–1,200 surge protector β€” cheap now, annoying later.
100+ people standing in 42 sqm is the densest WiFi spot in the office β€” the answer sizes that AP's capacity plan.
Printers want wired drops β€” adding them while the ceiling is open costs almost nothing.
A door-forced or over-temperature alert at 2 a.m. only matters if a named person responds to it.

Sources: open questions from all 13 expert briefs (rounds 1 & 2) plus the critic's 14 fold-in gaps, deduplicated 141 β†’ 40. Related pages: Risks ranks what happens if these stay unanswered; Timeline shows which week each answer is needed by.