Open Questions ยท Who Must Answer What
The 13 experts and the critic raised 141 raw open questions, deduplicated to 44. On Jul 2 the client answered 9 of them โ including two of the three blockers (building address, desk wiring) โ and those answers raised 3 new questions, leaving 38 open, grouped by the only thing that matters for getting them closed: who has to answer. Tick a question when it is answered โ state is saved in this browser. Items flagged W1 must be asked this week (Jul 6โ10) or the mid-August go-live slips.
Is the โฑ206,304 VAT-inc budget approved โ plus the remaining option calls (cold-spare AP โฑ23,000 ยท AV tier) and the decided recurring internet (โโฑ41,364/mo VAT-ex)? The equipment PO must go out this week: the APs and the 10G PoE++ switch are frequently 2โ4-week indent (import) items in the Philippines. Note the total banks โฑ90,000 (VAT-ex) on reused gear โ the 3 reused APs + gateway must be bench-tested now. (The other two former blockers โ building address and desk wiring โ were answered Jul 2, below.)
Answered client ยท 2026-07-02
Nine questions closed by the client's answer batch. Each is stated with its decision; three follow-up questions they raised are now in the open groups below.
1 ยท Paul / management
Decisions only management can make. Most of them gate a purchase order or an application that must leave this week.
2 ยท Landlord / building PMO
The building is now named โ Johndorf Tower, Cebu Business Park โ so the drafted 15-point PMO questionnaire can go out today (route via Princess Dacillo). These are the decision-critical items from it.
3 ยท Fit-out contractor
The construction schedule is the second critical path next to the ISP. Everything here is one site meeting. The fit-out package includes the server rack, 24-port patch panel and Cat6-in-conduit drops at no cost to this project โ the last four questions pin that provision down.
4 ยท Installation vendor(s)
Prowatcher โ kept as the probable installer (client, Jul 2), subject to the survey-based re-quote below โ plus the UniFi distributors (MEC, iConnect). Competing cabling bids are now optional leverage.
5 ยท ISP(s)
The plan is decided (Jul 2): RISE Dedicated 100 Mbps primary + PLDT Broadband 200 Mbps backup, both already in the Johndorf Tower riser. What remains is contract terms, physical handoff, and path diversity.
6 ยท Cebu ops team on the ground
Things only someone physically in Cebu (Xerxis / office admin) can check or own.
Sources: open questions from all 13 expert briefs (rounds 1 & 2) plus the critic's 14 fold-in gaps, deduplicated 141 โ 40, plus 4 fit-out-provision questions added Jul 2 (44 total); the client's Jul 2 answer batch closed 9 and raised 3 new (path diversity, RISE terms, aircon owner) โ 38 open. Related pages: Risks ranks what happens if these stay unanswered; Timeline shows which week each answer is needed by.