Deployment Dossier ยท Cebu Office WiFi 7
Professional UniFi WiFi 7 deployment plan for Software Club's new Cebu office, built from the architect's DRAFT 02 floor plan and an 8-domain research sweep (hardware, RF/regulatory, cabling, ISPs, vendors, timeline, cost, risk). Audience: Paul (owner), the Cebu ops team, and candidate installation vendors. Everything here is self-hosted and self-contained โ no external dependencies.
Design at a glance
WiFi
7ร U7 Pro XGS (tri-band WiFi 7, 8 spatial streams, 10GbE uplink, dedicated spectral-scan radio) โ 3 along the 27 m open-plan spine, 4 covering conference, meeting, reception and amenity zones. ~43 devices/AP at full occupancy. 6 GHz is legal in the Philippines verified โ lower 500 MHz only (NTC MC 002-07-2024), run as 80 MHz PSC channels; 5 GHz anchored on non-DFS channels (Mactan-Cebu airport ~10 km).
Backbone
UCG-Fiber reused as gateway + UniFi controller (2ร 10G SFP+, 5 Gbps IDS/IPS) uplinked over SFP+ DAC to a USW-Pro-XG-10-PoE (10ร 10GbE PoE++, 400 W budget, 1U). 8ร Cat6A drops (7 APs + 1 spare), 193 m measured incl. slack, every run < 35 m. Dual WAN: business fiber primary + 5G CPE failover.
Server room
Central 4.97 sqm room as the star point. 12U wall rack, 24-port Cat6A patch panel, PDU, and a 1โ1.5 kVA line-interactive pure-sine UPS with AVR (~15โ30 min runtime at ~300 W load โ essential against Cebu brownouts). Requires its own circuit, cooling and earthing at handover.
- โฅ5 APs requested โ 7 recommended. Coverage math says 5 is enough (530.62 sqm รท 160 sqm/AP), but capacity math doesn't: ~150 staff โ 300โ450 concurrent devices โ 6โ8 APs at a healthy 40โ60 clients/AP, and 150 seats sit in a 178 sqm strip at 1.2 sqm/seat.
- 8-port switch requested โ 10-port. 7 APs ร 29 W PoE++ nameplate = 203 W > the USW-Pro-XG-8-PoE's 155 W budget โ the 8-port locks the design at 5 APs. USW-Pro-XG-10-PoE: 400 W, ~97 W headroom. verified
- Prowatcher's โฑ1,500 PoE+ injector is the wrong PoE class. The U7 Pro XGS requires PoE++ (802.3bt, 29 W max); an 802.3at injector cannot power it. Any new quote must delete this line โ all APs power from the PoE++ switch. verified
Do this week by Fri Jul 10
The critical path is ISP provisioning + the ceiling-close window, not equipment. Five actions this week protect the Aug 15 deadline; details and owners on the Timeline.
Dossier contents
2D Plan & Coverage interactive
Vector floor plan with a live RF heatmap per band โ drag APs, simulate failures, auto-measured cable schedule.
3D Walkthrough
Walk the office in 3D: rooms, desks, AP positions and mounting heights in context.
Cabling
8ร Cat6A drops, 193 m measured routing, buy quantities, termination and 10G certification requirements.
BOM & Costs
Line-by-line bill of materials in โฑ, VAT-ex/inc, verified vs estimated prices, budget-floor alternative.
Vendors & Quote
Prowatcher's Jan-2026 quote dissected (incl. the PoE-class error), PH distributors, and the dual-quote strategy.
Network Design
VLANs, SSIDs (corp 802.1X / guest / IoT), channel plan, RF settings, dual-WAN failover.
Timeline
Week-by-week Gantt (W1 Jul 6 โ W6 Aug 14) with milestones, owners and the critical path.
Open Questions needs Paul
The decisions only Paul can make โ desk wiring, budget approval, ISP terms, old-office cutover date.
Risks
Ranked risk register with mitigations: ISP slip, ceiling closure, stock, PoE budget, single points of failure.
Knowledge Base
Verified specs, PH regulatory references, pricing anchors and the full source list behind every claim.
Status
Done as of 2026-07-02
- DRAFT-02 floor plan digitized to vector (rooms, desks, core notch)
- RF design: 7-AP placement, channel plan, propagation model
- Full BOM priced in โฑ with verified/estimate flags
- Vendor & quote analysis (incl. PoE-class error found)
- 6-week timeline with critical path and PH holiday check
Pending blocking
- Paul's answers to the open questions โ esp. desk wiring (changes the switch layer entirely) and budget approval
- Survey-based quotes from Prowatcher + a structured-cabling contractor
- Equipment PO โ not issued; stock is indent, clock is running
- ISP applications (RISE + backup) โ not lodged
- Ceiling-closure date from the fit-out GC โ not confirmed
Sources & data
Hardware specs verified against techspecs.ui.com and store.ui.com (U7 Pro XGS, UCG-Fiber, USW-Pro-XG-8/10-PoE); 6 GHz regulatory status from NTC Memorandum Circular 002-07-2024; PH pricing anchored to Prowatcher's Jan-2026 quote (โฑ59,897.60 VAT-inc, old office) and distributor/retail checks (MEC Networks, iConnect, PC Express); timeline benchmarks from RISE/PLDT/Converge public data and Proclamation No. 1006 (2026 holidays). Items marked estimate are extrapolations pending quotes. Full citation list: Knowledge Base.