Deployment Dossier Β· Cebu Office WiFi 7

Professional UniFi WiFi 7 deployment plan for Software Club's new Cebu office β€” Johndorf Tower, 12F Units 2&3, Cebu Business Park (Biliran Rd, Brgy Luz, Cebu City) β€” built from the architect's DRAFT 02 floor plan and an 8-domain research sweep (hardware, RF/regulatory, cabling, ISPs, vendors, timeline, cost, risk). Audience: Paul (owner), the Cebu ops team (local contact: Princess Dacillo), and the installation vendor. Everything here is self-hosted and self-contained β€” no external dependencies.

530.62 sqm
Floor area Β· 17.64 Γ— 37.54 m
133 desks
~150 staff Β· 300–450 devices
7Γ— U7 Pro XGS
WiFi 7 APs Β· 4 new + 3 reused
β‚±206,304
Recommended capex Β· VAT-inc
44 days
To deadline Β· Sat Aug 15

Design at a glance

WiFi

7Γ— U7 Pro XGS (tri-band WiFi 7, 8 spatial streams, 10GbE uplink, dedicated spectral-scan radio) β€” 3 along the 27 m open-plan spine, 4 covering conference, meeting, reception and amenity zones. ~43 devices/AP at full occupancy. 6 GHz is legal in the Philippines verified β€” lower 500 MHz only (NTC MC 002-07-2024), run as 80 MHz PSC channels; 5 GHz anchored on non-DFS channels (Mactan-Cebu airport ~10 km).

2D plan & live coverage β†’

Backbone

UCG-Fiber reused as gateway + UniFi controller (2Γ— 10G SFP+, 5 Gbps IDS/IPS) uplinked over SFP+ DAC to a USW-Pro-XG-10-PoE (10Γ— 10GbE PoE++, 400 W budget, 1U). 8Γ— Cat6 drops in conduit β€” fit-out-provided at β‚±0 (7 APs + 1 spare), 193 m measured incl. slack, every run < 35 m; Cat6 carries 10G at these lengths (TSB-155), every link 10G-qualification-tested. Dual WAN (decided Jul 2): RISE Dedicated 100 Mbps + PLDT Broadband 200 Mbps in load-balance β€” real-time traffic pinned to RISE, bulk spills to PLDT; optional 5G CPE bridge.

Cabling β†’ Β· Network design β†’

Server room

Central 4.97 sqm room as the star point. Server rack + 24-port patch panel fit-out-provided (rack size TBC), PDU, and a 1–1.5 kVA line-interactive pure-sine UPS with AVR (~15–30 min runtime at ~300 W load β€” essential against Cebu brownouts). Requires its own circuit, cooling and earthing at handover.

Full BOM & costs β†’

Where this plan deviates from the brief

Do this week by Fri Jul 10

The critical path is ISP provisioning + the ceiling-close window, not equipment. Five actions this week (one now optional) protect the Aug 15 deadline; details and owners on the Timeline.

Dossier contents

2D Plan & Coverage interactive

Vector floor plan with a live RF heatmap per band β€” drag APs, simulate failures, auto-measured cable schedule.

3D Walkthrough

Walk the office in 3D: rooms, desks, AP positions and mounting heights in context.

Cabling

8Γ— fit-out-provided Cat6-in-conduit drops, 193 m measured routing, the C1–C8 schedule for the GC, and the Cat6-vs-10G qualification-testing requirements.

BOM & Costs

Line-by-line bill of materials in β‚±, VAT-ex/inc, verified vs estimated prices, budget-floor alternative.

Vendors & Quote

Prowatcher's Jan-2026 quote dissected (incl. the PoE-class error), PH distributors, and the dual-quote strategy.

Network Design

VLANs, SSIDs (corp 802.1X / guest / IoT), channel plan, RF settings, dual-WAN failover.

Timeline

Week-by-week Gantt (W1 Jul 6 β†’ W6 Aug 14) with milestones, owners and the critical path.

Open Questions needs Paul

9 answered Jul 2 (address, WiFi-only, ISP plan, Intune, guest, installer…); 38 still open β€” budget approval β‚±206,304 is the last blocker.

Risks

Ranked risk register with mitigations: ISP slip, ceiling closure, stock, PoE budget, single points of failure.

Knowledge Base

Verified specs, PH regulatory references, pricing anchors and the full source list behind every claim.

Status

Done as of 2026-07-02

  • DRAFT-02 floor plan digitized to vector (rooms, desks, core notch)
  • RF design: 7-AP placement, channel plan, propagation model
  • Full BOM priced in β‚± with verified/estimate flags
  • Vendor & quote analysis (incl. PoE-class error found)
  • 6-week timeline with critical path and PH holiday check
  • Client answers Jul 2: address (Johndorf Tower 12F), WiFi-only confirmed, ISP plan decided (RISE Ded-100 + PLDT BB-200 β‰ˆβ‚±41,364/mo), Intune EAP-TLS go, no guest SSID, Prowatcher kept (probable)

Pending blocking

  • Budget sign-off β‚±206,304 VAT-inc β€” the single remaining blocking question (address + desk-wiring answered Jul 2)
  • Survey-based re-quote from Prowatcher (kept, probable) β€” competing quotes now optional
  • Equipment PO β€” not issued; stock is indent, clock is running
  • ISP orders β€” RISE Ded-100 + PLDT BB-200 decided, contracts not yet signed/lodged
  • Ceiling-closure date from the fit-out GC β€” not confirmed

Sources & data

Hardware specs verified against techspecs.ui.com and store.ui.com (U7 Pro XGS, UCG-Fiber, USW-Pro-XG-8/10-PoE); 6 GHz regulatory status from NTC Memorandum Circular 002-07-2024; PH pricing anchored to Prowatcher's Jan-2026 quote (β‚±59,897.60 VAT-inc, old office) and distributor/retail checks (MEC Networks, iConnect, PC Express); timeline benchmarks from RISE/PLDT/Converge public data and Proclamation No. 1006 (2026 holidays). Items marked estimate are extrapolations pending quotes. Full citation list: Knowledge Base.